Solar Product vs Performance Warranty: Build a Claim That Matches the Promise

Understand solar product, performance, inverter and workmanship warranties in India and build a claim with serials, data and contract terms.

Nikhil VermaUpdated: August 3, 2026Source links included · no dated re-check
Guide shortcuts

Jump to the part that matches your decision or check.

These shortcuts come from substantive sections already in this article; they are not generic category problems.

5 focused paths
See 1 more situation

Quick answer: A product warranty, power-performance warranty, inverter warranty and installer workmanship warranty cover different failures. Start by naming the symptom, identifying the failed component, preserving data and matching that evidence to one written promise. Do not begin with “the system makes less money than expected”—that can mix equipment, design, weather, tariff and consumption issues.

Safety line: do not climb onto a roof, unplug live DC connectors, open the inverter or defeat isolation equipment. Export monitoring data and arrange qualified inspection.

Five promises that are often bundled into one sales pitch

DocumentTypical subjectWhat it does not automatically cover
Module product warrantyManufacturing or material defect in a moduleLow output caused by shade, dirt, design or other equipment
Module performance warrantyMaximum degradation or minimum output under stated test conditionsYour household bill, annual rupee savings or whole-system uptime
Inverter/optimizer warrantyCovered failure of that deviceModules, mounting, wiring workmanship or grid outages
Installer workmanship warrantyInstallation defects such as specified wiring, mounting or sealing workA manufacturer’s internal component defect
Insurance or service planOnly the named accidental, weather, theft or maintenance eventsAnything excluded, depreciated or outside the policy period

Duration alone is a poor comparison. A long performance warranty with a narrow remedy can be less useful than a shorter product warranty with clear labour and logistics coverage.

Read the remedy, not just the year count

For every installed model, save the warranty PDF that was in force when it was sold and answer:

  • Who is the legal warrantor and where must a claim be filed?
  • Does registration or transfer to a new owner matter?
  • Which serial number, invoice and commissioning records are required?
  • How is a defect or degraded output tested, and by whom?
  • Can the warrantor repair, replace, provide a refurbished unit or pay a depreciated amount?
  • Who pays diagnosis, scaffolding, removal, packing, freight, customs, labour and reinstallation?
  • Do replacement parts inherit the original end date or receive a new term?
  • Which events are excluded: corrosion zone, unauthorised work, grid event, surge, flood, fire, pests or improper maintenance?

U.S. Department of Energy project guidance usefully tells asset owners to document underperformance and check whether repair/replacement, labour, removal, shipping and reinstallation are included. That is technical contract-reading guidance, not Indian warranty law; your signed Indian contracts and applicable law control.

A performance warranty is a measurement claim

Household generation below a salesperson’s forecast is not by itself proof that modules breached their performance curve. Annual energy depends on solar resource, orientation, shade, soiling, temperature, mismatch, inverter clipping, grid availability and downtime. The performance document may instead compare a module’s measured output with its warranted nameplate percentage under defined conditions.

Build a safe evidence ladder:

  1. Export daily/monthly generation and alarm history before an app reset or account transfer.
  2. Photograph serial labels and visible damage from a safe location; do not walk the roof.
  3. Compare inverter production with the utility/generation meter, accounting for different measurement points.
  4. Note changes: new shade, construction, long outages, cleaning, component replacement or loss of one string.
  5. Ask a qualified technician for a written fault isolation: module, connector/cable, inverter, meter, grid, design or maintenance.
  6. If claiming module performance, obtain the test method and result required by the manufacturer instead of inventing a home test.

ALMM and subsidy records are evidence—not a warranty substitute

MNRE’s live ALMM page identifies models/manufacturers eligible in the project categories covered by the ALMM order and is updated regularly. It does not promise that a particular consumer claim will be paid. For a government-assisted rooftop project, retain the portal application, vendor selection, installed model/serial records, invoices and commissioning documents alongside the current scheme requirements.

If the invoice model differs from the module installed or from the model recorded on the portal, freeze the evidence and ask the vendor to reconcile it in writing before anyone swaps labels or equipment.

Route the claim to the party that owns the failure

  1. Installer: ask for site inspection and fault isolation under the workmanship/service contract.
  2. Manufacturer: open the product or performance claim with the required serials and test evidence.
  3. Inverter service network: use the device error code, logs and model-specific procedure.
  4. Insurer: use the policy notice route for a covered external event; preserve damaged parts if instructed.

Send one chronology with installation date, first symptom, data gap, inspections and requested remedy. Ask each party to state whether it accepts responsibility, which clause it relies on, what additional evidence it needs, who bears each incidental cost and the next response date. A vague “system is underperforming” ticket invites vague answers.

Handover records that prevent the next dispute

  • itemised invoice and exact equipment schedule;
  • serial-number photos mapped to strings/components;
  • manufacturer and installer warranty PDFs;
  • design, single-line diagram and commissioning/test report;
  • monitoring owner credentials and historical export;
  • meter/DISCOM/portal approvals where applicable;
  • shutdown, cleaning and maintenance instructions;
  • service contacts and written allocation of access, freight and labour costs.

Official sources used

My FixWise checklist

Turn this guide into your case plan.

These items are pulled from this guide’s own evidence/action sections. Tick what you have, add a private note, and copy the plan when you need it.

Saved only on this deviceSaved just now
0 of 8 checked0%
What changed in this guide
  • July 23, 2026Tightened the search title while preserving the page intent and canonical URL.
  • July 20, 2026Distinguished product, workmanship and performance claims and added serial, output, exclusion and remedy evidence needed for a claim.
Content edited: August 3, 2026

Frequently Asked Questions

Does a performance warranty guarantee my electricity bill savings?
Usually no. It normally promises a defined module-output level under the manufacturer’s stated test conditions. Household savings also depend on weather, shade, soiling, inverter availability, system design, self-consumption, tariffs and downtime.
Who pays removal, shipping and reinstallation?
The written warranty and installer contract decide. A replacement module can still leave the owner paying diagnosis, access, freight, labour or reinstallation if those costs are excluded.
Does ALMM listing prove that a warranty claim will be honoured?
No. ALMM eligibility and warranty enforcement are different questions. Confirm the exact installed model on the current list where the scheme requires it, then separately read the manufacturer and installer contracts.
What evidence should I preserve before service?
Invoice, proposal, serial-number photos, warranty PDFs, commissioning report, single-line diagram, monitoring exports, meter readings, alarms, service tickets and safe photos of visible damage.